In the coming week, 17 road construction projects will be in full swing throughout the city. This work is necessary to repair damage and maintain the city's road network. Unfortunately, these measures also lead to traffic obstructions. In total, the city is taking care of around 490 kilometers of road network in Plauen.
New and modified construction measures:
- AlthaselbrunnFrom Monday, 02.09.2024, the second construction phase will begin. The area from house no. 14 to Seumestraße will then be closed to traffic. The one-way street will be closed. The passage to Haselbrunner Straße will also be closed. The 1st construction phase has been completed. The closure is expected to last until 02.10.2024.
- StresemannstrasseStresemannstraße will be closed on Thursday, 05.09.2024, in the area between Forststraße and Bahnhofstraße from 6.00 am to 10.00 am. A crane will be dismantled.
- FriesenwegFrom Wednesday, 04.09.2024, Friesenweg will be closed to traffic in the area between Möschwitzer Straße and Am Preißelpöhl. The main water pipe at house no. 19 will be relocated. The closure is expected to last until 13.09.2024.
- Max-Liebermann-StraßeFrom Wednesday, 04.09.2024, the Max-Liebermann will be closed. The road will be repaired. The closure is expected to last until 01.11.2024.
- Neundorfer Street 91: The thoroughfare between Liebknechtstraße and Ferdinand-Schill-Straße is fully closed here. The closure is expected to last until 30.09.2024.
- Middle roadMittelstraße is fully closed between Am Teich and Oberlosaer Weg. The reason is work on a gas service connection. The closure is expected to last until 06.09.2024.
- Unterlosaer StraßeFrom Monday, 02.09.2024, Unterlosaer Straße will be fully closed between Findeisenstraße and Am Reuthhübel. Work is being carried out on the water service connection. The closure is expected to last until 10.09.2024.
An overview of all construction sites can be found online at www.plauen.de/baustellen.
Please note that the dates given are not binding and may change due to unforeseen circumstances.
The city asks all road users for their understanding and patience.
- Althaselbrunn: The second construction phase will begin on Monday, 02.09.2024. The area from house no. 14 to Seumestraße will then be closed to traffic. The one-way street will be closed. The passage to Haselbrunner Straße will also be closed. The first construction phase has been completed.
The closure is expected to last until 02.10.2024 - Stresemannstrasse: A crane will be dismantled here on Thursday. Stresemannstraße will be closed in the area between Forststraße and Bahnhofstraße from 6.00 am to 10.00 am.
- Friesenweg: From Wednesday, 04.09.2024, Friesenweg will be closed to traffic in the area between Möschwitzer Straße and Am Preißelpöhl. The main water pipe at house no. 19 will be relocated.
The closure is expected to last until 13.09.2024
- Max-Liebermann-Straße: From Wednesday, 04.09.2024, the Max-Liebermann will be closed. The road will be repaired. The closure is expected to last until 01.11.2024
- Neundorfer Straße 91: The thoroughfare between Liebknechtstraße and Ferdinand-Schill-Straße is fully closed here. The closure is expected to last until 30.09.2024
- Mittelstraße: Mittelstraße is fully closed between Am Teich and Oberlosaer Weg. This is due to work on a gas service connection. The closure is expected to last until 06.09.2024
- Unterlosaer Straße: From Monday, 02.09.2024, Unterlosaer Straße will be fully closed between Findeisenstraße and Am Reuthhübel. Work is being carried out on the water service connection. The closure is expected to last until 10.09.2024
In Plauen, 17 road construction projects are underway in the coming week to repair damage and maintain the city's road network. However, this work will lead to traffic disruptions, as the city has a total of around 490 kilometers of roads to maintain.
New and modified construction measures affect various roads in the city area. The second construction phase in Althaselbrunn will begin on 02.09.2024, whereby the area from house no. 14 to Seumestraße will be closed to traffic. Stresemannstraße will be closed on 05.09.2024 between Forststraße and Bahnhofstraße for the dismantling of a crane.
In addition, Friesenweg will be closed to traffic from 04.09.2024 in the area between Möschwitzer Straße and Am Preißelpöhl in order to relocate the main water pipe. Max-Liebermann-Straße will be closed from the same day for road rehabilitation work, probably until 01.11.2024.
Further closures affect Neundorfer Straße 91, Mittelstraße and Unterlosaer Straße, where various work is being carried out on house connections. A detailed overview of all roadworks and closures is available online at www.plauen.de/baustellen.
Please note that the dates given are not binding and may change due to unforeseen circumstances. The city asks all road users for their understanding and patience during the construction work.